Why create visual aids?
For key processes outlined in the contract, diagrams are a useful way to navigate important requirements and considerations. You can specify if there is a particular process you would like us to visualise for you.
Example
Below, is an example diagram outlining the process for submitting a notice of delay for the FIDIC Redbook (Second Edition 2017).
graph TD
A[Contractor experiences delay] --> B[Contractor gives Notice to Engineer]
B -->|Within 28 days| C[Engineer responds]
C -->|Within 14 days| D[Contractor submits fully detailed claim]
D -->|Within 84 days| E[Engineer reviews claim]
E --> F[Engineer may request more details]
F --> G[Engineer determines extension of time]
G -->|Within 42 days| H{Contractor agrees?}
H -->|Yes| I[Process ends]
H -->|No| J[Contractor gives Notice of Dissatisfaction]
J -->|Within 28 days| K[Dispute may be referred to Dispute Board]
style A fill:#ECE6DC,stroke:#333,stroke-width:2px
style B fill:#ECE6DC,stroke:#333,stroke-width:2px
style C fill:#ECE6DC,stroke:#333,stroke-width:2px
style D fill:#ECE6DC,stroke:#333,stroke-width:2px
style E fill:#ECE6DC,stroke:#333,stroke-width:2px
style F fill:#ECE6DC,stroke:#333,stroke-width:2px
style G fill:#ECE6DC,stroke:#333,stroke-width:2px
style H fill:#ECE6DC,stroke:#333,stroke-width:2px
style I fill:#ECE6DC,stroke:#333,stroke-width:2px
style J fill:#ECE6DC,stroke:#333,stroke-width:2px
style K fill:#ECE6DC,stroke:#333,stroke-width:2px