Explore each example from its overview, then inspect the review, period position and linked records. All projects and assessments are fictional.Discuss your project
Bid · pre-submission reviewEGH-B01
Eastgate Health Centre
Concrete frame bid
Review snapshot30 September 2026
The bid at a glance
The scope and contract come first. The readiness review shows what still needs a response.
No tender submitted
A two-storey community health centre of approximately 4,000 m² gross internal area. The package covers reinforced-concrete foundations, ground-floor slabs, the first-floor frame and precast stairs, with temporary works and precast-stair connection design. The primary permanent frame is designed by others.
Proposed contract
JCT Design and Build Sub-Contract 2024
Contract documents
DBSub/A + DBSub/C 2024 Under a JCT DB 2024 main contract
Working bid value
£1,450,000 excluding VAT
Priced design responsibility
Temporary works and precast-stair connections. Primary permanent frame by others.
Make the priced scope explicit.
Resolve the slab information and design responsibilities before finalising the offer.
Coordinated slab detail and penetration schedule are incomplete.
Submission evidence8 / 10
Rebar supplier quote expires before the intended order date.
16 + 18 + 14 + 12 + 8 = 68Illustrative review-team assessment of evidence completeness. Scores are points earned against the stated maximum; the five category maximums total 100 points; the sample scores total 68. This is not a probability of winning or an approval to bid.
Slab S1 is a 600 m² subset of this approximately 4,000 m² building: 30 × 20 m. Concrete is 180 m³ at 300 mm or 240 m³ at 400 mm, a 60 m³ difference before waste.
Next action
Seek a coordinated written clarification. Carry both quantity scenarios and make the priced assumption explicit until the answer is received.
Estimator / design manager · Target 2 Oct
Inspect the source evidenceClarification open
Clarification openFictional source excerpt
Clarification open
Drawing EGH-S102 P02: 300 mm. Specification §2.1 P02: 400 mm. TQ-012 remains open.
Drawing EGH-S102 P02300 mm
600 m² × 0.30 m = 180 m³
Specification §2.1 P02400 mm
600 m² × 0.40 m = 240 m³
60 m³ difference before waste. Neither source is selected as the governing thickness. S1 is a 600 m² subset of the building.
Condensed fictional record for this example.
BID-02High priority
Design responsibility extends beyond the priced scope
Unpriced design work and responsibility may sit outside the current allowance.
Next action
Reconcile the design-responsibility matrix with the draft amendments. Obtain commercial and legal review; price the agreed scope or qualify it clearly.
Commercial manager · Target 5 Oct
Inspect the source evidenceAmendment under review
Amendment under reviewFictional source excerpt
Amendment under review
Proposed amendment AM-07 asks for responsibility for the primary permanent frame; the priced designed portion covers temporary works and precast-stair connections only.
Unpriced design work and responsibility may sit outside the current allowance.
Condensed fictional record for this example.
BID-03Medium priority
Access dates do not support the proposed pour sequence
The first concrete pour and crane mobilisation may need resequencing.
Next action
Confirm phased access, crane setup and delivery slots. Submit a priced programme assumption and identify the effect if the later access date applies.
Planner / project manager · Target 5 Oct
Inspect the source evidenceAccess date unconfirmed
Access date unconfirmedFictional source excerpt
Access date unconfirmed
Tender programme TP-02 starts the frame on 2 November; logistics note L-03 only releases the full working area on 9 November.
The first concrete pour and crane mobilisation may need resequencing.
Condensed fictional record for this example.
BID-04Medium priority
Rebar quotation expires before the order date
The bid could carry a supplier price that is no longer available when ordered.
Next action
Obtain an extended quotation or refresh the rate. Record the validity and procurement assumption in the tender review.
Buyer / estimator · Target 6 Oct
Inspect the source evidenceQuote refresh required
Quote refresh requiredFictional source excerpt
Quote refresh required
Supplier quotation Q-118 is valid to 16 October; the current procurement plan places the order on 23 October.
The bid could carry a supplier price that is no longer available when ordered.
Condensed fictional record for this example.
Bid review snapshot: 30 September 2026. Targets are internal review dates; the illustrative tender return is 9 October 2026. The score records evidence completeness and does not approve the bid.
Contract · live projectHEX-026 · South West England
Harbour Exchange
Concrete frame
Reporting periodSeptember 2026 · P05
The contract at a glance
A concrete-frame subcontract, from the original commitment to today’s delivery position.
Frame subcontractor view
A six-storey office building with a basement, approximately 20,000 m² gross internal floor area in total. The concrete-frame package includes foundations, reinforced-concrete cores, columns and slabs, precast stairs and temporary works.
Contract
JCT Design and Build Sub-Contract 2024
Contract documents
DBSub/A + DBSub/C 2024 Under JCT DB 2024
Designed portion
Temporary works and precast-stair connections. Primary frame by others.
Our view
Concrete-frame subcontractor. Main contractor issues instructions.
Position at 30 September
Level 3 slab pours are complete. Level 4 reinforcement and formwork are progressing; upper-level core work continues.
A concrete frame in deliveryAI-generated illustration of the project type. It is not a project photograph or a measured progress record.
Original contract price£7.50mBefore agreed variations
Original budget cost£6.75mIncluding project site overheads
Original margin£750k10.0% of original revenue
Planned duration27weeksApproximately · 18 May – 20 Nov 2026
Programme at a glance
Quantity-based progress · 30 September
3 points behind
Planned physical progress63%
Reported physical progress60%
Start18 May 2026
Contract completion20 November 2026
Scenario · 5 points/week25 November 2026
Scenario · 4 points/week9 December 2026
Two indicative completion scenarios, at 5 or 4 percentage points of progress per week. They require programme validation; the contract completion date is unchanged.
Margin is project contribution after site overheads, before corporate overheads and tax. Percentage is margin divided by revenue. Forecast cost includes £200k for unresolved change costs.
The £440k difference compares valued work with accrued costs. It is not cash or the final project margin. Valuation includes £40k of completed unagreed work.
Open VAL-05 · subcontractor’s valuation (application)30 September 2026
Base scope assessed £4,280,000 + agreed change work assessed £100,000 = £4,380,000 gross certified. PAY-05 is dated 5 October.
3% retention is £131,400; no other deductions are shown. Net certified is £4,248,600. Retention remains held under the sample terms; it is not lost revenue.
Condensed fictional record for this example.
Certified does not mean paid
Payment follow-up · 21 October
Net certified£4.249m
£4,248,600 after retention
Cash received£4.080m
Receipts reconciled to bank
Gross certified£4,380,000
Less 3% retention held−£131,400
Other deductions£0
Net certified£4,248,600
Less cash received−£4,080,000
Certified balance not received£168,600
The balance is not classified as overdue. Retention is held under the sample subcontract terms and is not lost revenue.
Open CASH-05 · receipts recordReconciled to 21 October 2026
Reconciled to 21 October 2026Fictional source excerpt
Receipts reconciled to 21 October
£4,080,000 cumulative cash received is reconciled to the bank. Against £4,248,600 net certified, £168,600 is not yet matched to a receipt.
Check the applicable dates and remittance before classifying the balance as overdue.
Physical progress is measured independently of value. The dashed line extends the recent rate; it is not a logic-linked forecast.
Open P05 · progress basis30 September 2026
30 September 2026Fictional source excerpt
Quantity-based, fixed-weight progress
Fixed baseline package weights: foundations 20%, cores 15%, frame floors 50%, stairs 10%, close-out 5%. Reported progress is quantity-based within each work package, independently of commercial valuation. Change value is tracked separately.
40 percentage points of physical progress remain. At 5 points per week, they take 8 weeks; at 4 points per week, they take 10 weeks. These are scenarios, not verified programme forecasts.
The first scenario extends the recent four-week rate. Both require checks of remaining sequencing, curing, striking, stair deliveries and handover.
→
Validate the sequence and test recovery.
Revised mezzanine details and later stair openings are constraining the current sequence. Their individual or combined effect on completion is not yet established.
Open P01 · programme and scenarioBaseline dates and recent-rate calculation
Baseline dates and recent-rate calculationFictional source excerpt
Start 18 May · contract completion 20 November 2026
186 calendar days between start and finish; 187 days counting both dates. Planned Monday–Friday calendar excludes the 25 May and 31 August bank holidays.
Reported progress rose from 40% on 2 September to 60% on 30 September: 20 percentage points in 4 weeks, or 5 points per week. At that recent rate, the remaining 40 points take 8 weeks, reaching 100% on 25 November. This is a recent-rate scenario. At 4 points per week, 10 weeks remain and completion moves to 9 December.
Simple progress extrapolation, not a logic-linked programme forecast or an assessed extension of time. Check remaining sequencing, curing, strikes, stair deliveries and handover before relying on the date. The contract completion date remains 20 November; no extension is assumed.
Condensed fictional record for this example.
All amounts exclude VAT. Project margin is revenue less project costs including site overheads, before corporate overheads and tax. Margin percentage is profit divided by revenue, not markup on cost.
Changes and instructions
Separate agreed value from open discussions. Open a change to inspect the instruction and supporting records.
Agreed£180k2 changes · in forecast revenue
In discussion · TBC£210k2 changes · excluded from revenue
Disagreed£35k1 change · excluded from revenue
5 changes shown
£425,000 full submitted / estimated value. This is the whole change register, including remaining work. Completed change work at 30 September is £160,000.
Additional perimeter upstands at Level 4. Formwork and reinforcement are partly complete; the remaining upstand work follows the Level 4 slab sequence.
Full submitted / estimated value£90,000
Completed by 30 September£30,000
Assessed / certified on 5 October£10,000
Remaining estimated work value£60,000
Next step · QS
Reconcile the £20,000 difference between £30,000 completed work and £10,000 assessed in PAY-05; retain £60,000 of remaining work in the forecast.
Supporting evidence: Instruction SI-011; Measured formwork and reinforcement sheet; Level 4 progress records.
Linked to V-002. Additional perimeter upstands at Level 4. Formwork and reinforcement are partly complete; the remaining upstand work follows the Level 4 slab sequence.
A 360 m² mezzanine zone changes from the tender precast arrangement to in-situ reinforced concrete, requiring revised propping and a new pour sequence.
Full submitted / estimated value£145,000
Completed by 30 September£30,000
Assessed / certified on 5 October£0
Remaining estimated work value£115,000
Next step · Commercial manager
Submit the reconciled concrete, reinforcement and propping build-up; link the sequence impact to the programme.
Supporting evidence: Drawing revision overlay; Temporary works revision TW-07; Labour and plant allocation; Concrete and rebar invoices.
ERI-018 · Mezzanine arrangement change3 Sep 2026
3 Sep 2026Fictional source excerpt
Mezzanine arrangement change
From: Employer's Agent to main contractor.
Record state: Upstream reference; passed down by SI-017.
Linked to V-003. A 360 m² mezzanine zone changes from the tender precast arrangement to in-situ reinforced concrete, requiring revised propping and a new pour sequence.
Condensed fictional record for this example.
SI-017 · Implement the revised mezzanine details4 Sep 2026
4 Sep 2026Fictional source excerpt
Implement the revised mezzanine details
From: Main contractor to frame subcontractor.
Record state: Instructed; valuation TBC.
Linked to V-003. A 360 m² mezzanine zone changes from the tender precast arrangement to in-situ reinforced concrete, requiring revised propping and a new pour sequence.
ERI-018 is the upstream Employer’s Agent reference. SI-017 is the main contractor’s instruction to the frame subcontractor. The change is instructed; the valuation is still to be agreed.
Condensed fictional record for this example.
TW-07 · temporary works revisionLinked supporting record · V-003
Linked supporting record · V-003Fictional source excerpt
Revised propping arrangement
The changed in-situ mezzanine needs a revised temporary works and pour sequence. Keep the revision, review status and release record with the commercial change.
Eight new Level 4 service penetrations require revised reinforcement and trimming details before the upcoming slab pour. Initial coordination and preparation work is complete; most of the change remains to be built.
Full submitted / estimated value£65,000
Completed by 30 September£10,000
Assessed / certified on 5 October£0
Remaining estimated work value£55,000
Next step · QS / engineer
Agree the opening schedule and measure the additional trimming bars and formwork.
Linked to V-004. Eight new Level 4 service penetrations require revised reinforcement and trimming details before the upcoming slab pour. Initial coordination and preparation work is complete; most of the change remains to be built.
Condensed fictional record for this example.
V-005Stair-landing reworkHEX-S-520 C04 / RFI-032; no confirmed instructionDisagreed£35,000
What changed
Proposed changes to a stair-landing opening would require local formwork alterations. No changed work has been carried out. The contractor considers the proposed work included in the original coordination scope; the subcontractor disagrees.
Full submitted / estimated value£35,000
Completed by 30 September£0
Assessed / certified on 5 October£0
Remaining estimated work value£35,000
Next step · Commercial manager
Reconcile the tender scope and revision history, request a written decision and keep the position separate from agreed revenue.
Supporting evidence: Tender scope matrix; Before / after drawing record; Estimate build-up / proposed method and resources; RFI-032 correspondence.
RFI-032 · Confirm stair-landing scope and formal direction15 Sep 2026
15 Sep 2026Fictional source excerpt
Confirm stair-landing scope and formal direction
From: Frame subcontractor.
Record state: Open clarification; not an instruction.
Linked to V-005. Proposed changes to a stair-landing opening would require local formwork alterations. No changed work has been carried out. The contractor considers the proposed work included in the original coordination scope; the subcontractor disagrees.
Condensed fictional record for this example.
Agreed values are £180k. In-discussion values (£210k) and disagreed value (£35k) total £245k and are excluded from forecast revenue. Completed change work is £120k agreed plus £40k unagreed; £100k has been assessed / certified. Instruction status and valuation agreement are separate.
Trace the direction through the right contract.
ERI-018 is the Employer’s Agent’s upstream reference. SI-017 passes the mezzanine change from the main contractor to the frame subcontractor. RFI-032 remains an open clarification and is not an instruction.
Clear owners and specific actions, linked to the records that explain why.
6 actions shown
01
Reconcile the £180k valuation gap
Base measurement £120k, V-002 agreed work £20k and completed unagreed work £40k (V-003 £30k + V-004 £10k) are not in the 5 October gross assessment.
Action: Prepare a line-by-line VAL-05 / PAY-05 reconciliation with measurements and the agreed change register.
Project QSTarget 23 Oct 2026A-01
High priority02
Complete the mezzanine change record
V-003 is instructed but its £145k valuation is still under discussion.
Action: Link the drawing revision, instruction, daily labour and plant, production quantities, invoices and temporary works records to V-003.
Site manager / QSTarget 22 Oct 2026A-02
High priority03
Verify required delay notices and close gaps
The revised sequence may affect completion. Existing notice history and evidence of service need verification; the dashboard does not confirm compliance.
Action: Have the commercial manager, with the appropriate contract or legal adviser, urgently check notices already issued, service records, the executed subcontract, amendments and applicable timing. Close any gaps and issue the appropriate notice if required. Do not assume compliance or an agreed extension of time.
Commercial managerTarget 22 Oct 2026A-03
High priority04
Show the programme impact and test recovery
The recent-rate scenario reaches 25 November, 5 calendar days / 3 working days after baseline; the slower-rate sensitivity reaches 9 December, 19 calendar days / 13 working days after baseline. Neither is a verified programme forecast.
Action: Update the logic-linked programme with actual dates, mezzanine activities, stair deliveries and curing / strike durations. Test safe resequencing and record effects on follow-on trades.
Planner / project managerTarget 23 Oct 2026A-04
High priority05
Close the stair-landing scope question
V-005 is disputed and there is no confirmed instruction.
Action: Assemble the tender scope matrix and drawing revision trail, seek written clarification and record the commercial response.
Commercial managerTarget 26 Oct 2026A-05
Medium priority06
Confirm receipt of the certified balance
At the 21 October cash follow-up, £168,600 net certified has not yet been matched to a receipt.
Action: Check the applicable payment dates and remittance with accounts; reconcile the receipt or record the specific follow-up needed. Do not label the balance overdue without checking.
Accounts / QSTarget 23 Oct 2026A-06
Medium priority
Live-project actions were reviewed on 21 October 2026. Due dates are illustrative internal targets, not contractual notice or payment deadlines. Cost, valuation and progress are at 30 September; certification is dated 5 October and receipts are reconciled to 21 October.