02 / Project Intelligence

Project portfolio

See the position. Follow the evidence. Know what needs attention.

Reporting periodSeptember 2026
2 sample projects1 bid1 live contract

Bids

Understand the commitment before you make it.

1
EGH-B01Pre-submission review

Eastgate Health Centre

Concrete frame bid

Two-storey community health centre, approximately 4,000 m². Foundations, floor frame and precast stairs.

JCT Design and Build Sub-Contract 2024

A clear bid starts with the scope.Four open findings link to the information and response needed.
Working bid value£1.45mBefore unresolved qualifications
Review readiness68/ 100Evidence completeness

4 open findings. Scope, design responsibility, access and price validity.

Snapshot · 30 Sep 2026
Tender return · 9 Oct 2026
Open bid

Contracts

Live projects · connect delivery to the commercial position.

1
HEX-026Live project

Harbour Exchange

Concrete frame

Six-storey office building with a basement, approximately 20,000 m² in total. Foundations, frame and stairs.

JCT Design and Build Sub-Contract 2024

Illustrative concrete frame with reinforced-concrete columns, floor slabs and a tower crane
AI-generated illustration · not a project photograph
Original contract price£7.50m18 May – 20 November 2026
Reported physical progress60%63% planned at 30 September

3 points behind plan. Review the commercial position, changes and recovery actions.

Period 05 · September 2026Open contract
Explore each example from its overview, then inspect the review, period position and linked records. All projects and assessments are fictional.Discuss your project
Bid · pre-submission reviewEGH-B01

Eastgate Health Centre

Concrete frame bid

Review snapshot30 September 2026

The bid at a glance

The scope and contract come first. The readiness review shows what still needs a response.

No tender submitted

A two-storey community health centre of approximately 4,000 m² gross internal area. The package covers reinforced-concrete foundations, ground-floor slabs, the first-floor frame and precast stairs, with temporary works and precast-stair connection design. The primary permanent frame is designed by others.

Proposed contract
JCT Design and Build Sub-Contract 2024
Contract documents
DBSub/A + DBSub/C 2024
Under a JCT DB 2024 main contract
Working bid value
£1,450,000 excluding VAT
Priced design responsibility
Temporary works and precast-stair connections.
Primary permanent frame by others.

Make the priced scope explicit.

Resolve the slab information and design responsibilities before finalising the offer.

Explore the four findings
68out of 100

Review readiness

An illustrative review-team assessment of evidence completeness.

Action needed

The five category maximums total 100 points. This is not a probability of winning or an approval to bid.

See the scoring method
First action target2 OctScope clarification
Final action target6 OctQuote refresh
Tender return9 Oct2026

Review detail

The category score, source information and next action are shown together.

How 68 / 100 is built

Points earned / points available

Manual assessment
Scope and quantities16 / 25

Slab thickness conflict remains open.

Commercial terms18 / 25

Proposed design liability amendment needs agreement.

Programme and access14 / 20

Working-area release dates are not confirmed.

Design information12 / 20

Coordinated slab detail and penetration schedule are incomplete.

Submission evidence8 / 10

Rebar supplier quote expires before the intended order date.

16 + 18 + 14 + 12 + 8 = 68Illustrative review-team assessment of evidence completeness. Scores are points earned against the stated maximum; the five category maximums total 100 points; the sample scores total 68. This is not a probability of winning or an approval to bid.

Four findings to resolve

2 high priority · 2 medium priority

  1. 01

    Two slab thicknesses in the tender pack

    Clarification open · Estimator / design manager

    Inspect finding 01
  2. 02

    Design responsibility extends beyond the priced scope

    Amendment under review · Commercial manager

    Inspect finding 02
  3. 03

    Access dates do not support the proposed pour sequence

    Access date unconfirmed · Planner / project manager

    Inspect finding 03
  4. 04

    Rebar quotation expires before the order date

    Quote refresh required · Buyer / estimator

    Inspect finding 04
BID-01High priority

Two slab thicknesses in the tender pack

Slab S1 is a 600 m² subset of this approximately 4,000 m² building: 30 × 20 m. Concrete is 180 m³ at 300 mm or 240 m³ at 400 mm, a 60 m³ difference before waste.

Next action

Seek a coordinated written clarification. Carry both quantity scenarios and make the priced assumption explicit until the answer is received.

Estimator / design manager · Target 2 Oct
Inspect the source evidenceClarification open
Clarification openFictional source excerpt

Clarification open

Drawing EGH-S102 P02: 300 mm. Specification §2.1 P02: 400 mm. TQ-012 remains open.

Drawing EGH-S102 P02300 mm

600 m² × 0.30 m = 180 m³

Specification §2.1 P02400 mm

600 m² × 0.40 m = 240 m³

60 m³ difference before waste. Neither source is selected as the governing thickness. S1 is a 600 m² subset of the building.

Condensed fictional record for this example.

BID-02High priority

Design responsibility extends beyond the priced scope

Unpriced design work and responsibility may sit outside the current allowance.

Next action

Reconcile the design-responsibility matrix with the draft amendments. Obtain commercial and legal review; price the agreed scope or qualify it clearly.

Commercial manager · Target 5 Oct
Inspect the source evidenceAmendment under review
Amendment under reviewFictional source excerpt

Amendment under review

Proposed amendment AM-07 asks for responsibility for the primary permanent frame; the priced designed portion covers temporary works and precast-stair connections only.

Unpriced design work and responsibility may sit outside the current allowance.

Condensed fictional record for this example.

BID-03Medium priority

Access dates do not support the proposed pour sequence

The first concrete pour and crane mobilisation may need resequencing.

Next action

Confirm phased access, crane setup and delivery slots. Submit a priced programme assumption and identify the effect if the later access date applies.

Planner / project manager · Target 5 Oct
Inspect the source evidenceAccess date unconfirmed
Access date unconfirmedFictional source excerpt

Access date unconfirmed

Tender programme TP-02 starts the frame on 2 November; logistics note L-03 only releases the full working area on 9 November.

The first concrete pour and crane mobilisation may need resequencing.

Condensed fictional record for this example.

BID-04Medium priority

Rebar quotation expires before the order date

The bid could carry a supplier price that is no longer available when ordered.

Next action

Obtain an extended quotation or refresh the rate. Record the validity and procurement assumption in the tender review.

Buyer / estimator · Target 6 Oct
Inspect the source evidenceQuote refresh required
Quote refresh requiredFictional source excerpt

Quote refresh required

Supplier quotation Q-118 is valid to 16 October; the current procurement plan places the order on 23 October.

The bid could carry a supplier price that is no longer available when ordered.

Condensed fictional record for this example.

Bid review snapshot: 30 September 2026. Targets are internal review dates; the illustrative tender return is 9 October 2026. The score records evidence completeness and does not approve the bid.

Contract · live projectHEX-026 · South West England

Harbour Exchange

Concrete frame

Reporting periodSeptember 2026 · P05

The contract at a glance

A concrete-frame subcontract, from the original commitment to today’s delivery position.

Frame subcontractor view

A six-storey office building with a basement, approximately 20,000 m² gross internal floor area in total. The concrete-frame package includes foundations, reinforced-concrete cores, columns and slabs, precast stairs and temporary works.

Contract
JCT Design and Build Sub-Contract 2024
Contract documents
DBSub/A + DBSub/C 2024
Under JCT DB 2024
Designed portion
Temporary works and precast-stair connections. Primary frame by others.
Our view
Concrete-frame subcontractor.
Main contractor issues instructions.

Position at 30 September

Level 3 slab pours are complete. Level 4 reinforcement and formwork are progressing; upper-level core work continues.

Illustrative six-storey concrete frame under construction with reinforced-concrete columns, slabs, exposed reinforcement and a tower crane
A concrete frame in deliveryAI-generated illustration of the project type. It is not a project photograph or a measured progress record.
Original budget cost£6.75mIncluding project site overheads
Original margin£750k10.0% of original revenue
Planned duration27weeksApproximately · 18 May – 20 Nov 2026

Programme at a glance

Quantity-based progress · 30 September

3 points behind
Planned physical progress63%
Reported physical progress60%
Start18 May 2026
Contract completion20 November 2026
Scenario · 5 points/week25 November 2026
Scenario · 4 points/week9 December 2026

Two indicative completion scenarios, at 5 or 4 percentage points of progress per week. They require programme validation; the contract completion date is unchanged.

Inspect the programme basis

Current commercial outlook

Agreed revenue and forecast costs

Excludes open revenue
Forecast revenue£7.68m

£7.50m original + £180k agreed changes

Forecast final cost£7.02m

£4.12m incurred + £2.90m to complete

Forecast contribution margin£660,000 · 8.6%
Original margin£750,000 · 10.0%
Unresolved change value£245,000 excluded

Margin is project contribution after site overheads, before corporate overheads and tax. Percentage is margin divided by revenue. Forecast cost includes £200k for unresolved change costs.

Inspect the September position

September 2026 position

Cost, valuation and physical progress at 30 September. Certification and receipts are shown separately.

Cumulative · Period 05
Work position30 Sep 2026Valuation · cost · progress
Assessment5 Oct 2026PAY-05 · September work
Cash follow-up21 Oct 2026Receipts reconciled to bank
Cost incurred£4.12mInvoices + accruals · 30 Sep
Gross certified£4.38mAssessment dated 5 Oct
Cash received£4.08mReceipts reconciled to 21 Oct

Cost against valuation

Cumulative at 30 September · both exclude VAT

Subcontractor’s gross valuation£4,560,000
Cost incurred£4,120,000
September valuation movement+£1,440,000
September cost movement+£1,300,000
Valuation less incurred cost£440,000

The £440k difference compares valued work with accrued costs. It is not cash or the final project margin. Valuation includes £40k of completed unagreed work.

Open VAL-05 · subcontractor’s valuation (application)30 September 2026
30 September 2026Fictional source excerpt

Value of work done at 30 September

Base scope £4,400,000 + agreed changes completed £120,000 + unagreed changes completed £40,000 = £4,560,000 gross valuation.

The completed unagreed work is V-003 £30,000 and V-004 £10,000. Open full change values are not all included as completed work.

Condensed fictional record for this example.

Open COST-05 · cost ledger30 September 2026
30 September 2026Fictional source excerpt

Cost incurred, including accruals

Recorded supplier/payroll invoices £3,770,000 + estimated accruals £350,000 = £4,120,000 cost incurred at 30 September.

This is an accrued cost position, not a statement of cash paid to suppliers.

Condensed fictional record for this example.

Valuation against certification

30 September work · assessed on 5 October

Gross valuation£4,560,000
Gross certified£4,380,000
Base measurement to reconcile£120,000
Agreed change work not yet assessed£20,000
Completed unagreed work excluded£40,000
Valuation / certification gap£180,000

These are gross, like-for-like figures before retention. The £20k agreed work difference is V-002; the £40k unagreed work is V-003 and V-004.

Follow the reconciliation action
Open PAY-05 · assessment5 October 2026
5 October 2026Fictional source excerpt

Assessment of September work

Base scope assessed £4,280,000 + agreed change work assessed £100,000 = £4,380,000 gross certified. PAY-05 is dated 5 October.

3% retention is £131,400; no other deductions are shown. Net certified is £4,248,600. Retention remains held under the sample terms; it is not lost revenue.

Condensed fictional record for this example.

Certified does not mean paid

Payment follow-up · 21 October

Net certified£4.249m

£4,248,600 after retention

Cash received£4.080m

Receipts reconciled to bank

Gross certified£4,380,000
Less 3% retention held−£131,400
Other deductions£0
Net certified£4,248,600
Less cash received−£4,080,000
Certified balance not received£168,600

The balance is not classified as overdue. Retention is held under the sample subcontract terms and is not lost revenue.

Open CASH-05 · receipts recordReconciled to 21 October 2026
Reconciled to 21 October 2026Fictional source excerpt

Receipts reconciled to 21 October

£4,080,000 cumulative cash received is reconciled to the bank. Against £4,248,600 net certified, £168,600 is not yet matched to a receipt.

Check the applicable dates and remittance before classifying the balance as overdue.

Condensed fictional record for this example.

Follow up the certified balance

Forecast cost and contribution

Current forecast · unresolved revenue excluded

Forecast cost£7.02m

Incurred £4.12m + remaining £2.90m

Forecast contribution margin8.6%

£660k / £7.68m forecast revenue

Forecast cost already includes £200k for unresolved change costs. The £245k unresolved variation value is excluded from revenue.

Inspect the £4.12m incurred costCost categories · 30 September 2026
Cost categories · 30 September 2026Fictional source excerpt
Cost incurred by category
Labour£1,240,000
Plant and temporary works£660,000
Concrete and reinforcement£1,650,000
Specialist work£270,000
Site overheads£300,000
Total£4,120,000

Condensed fictional record for this example.

Keep the forecast distinct from the valuation.

Forecast contribution margin includes the remaining work. Revenue is original price plus agreed variations only.

Inspect agreed and open changes

Programme: plan and actual

P01 baseline · P05 reported progress

−3 percentage points
Plan at 30 September63%
Actual at 30 September60%
Baseline planReported actualRecent-rate scenario

Physical progress is measured independently of value. The dashed line extends the recent rate; it is not a logic-linked forecast.

Open P05 · progress basis30 September 2026
30 September 2026Fictional source excerpt

Quantity-based, fixed-weight progress

Fixed baseline package weights: foundations 20%, cores 15%, frame floors 50%, stairs 10%, close-out 5%. Reported progress is quantity-based within each work package, independently of commercial valuation. Change value is tracked separately.

Package completion at 30 September
PackageWeightPlanActual
Foundations20%100%100%
Cores15%80%80%
Frame floors50%58%54%
Stairs10%20%10%
Close-out5%0%0%
Weighted total100%63%60%

Plan: 20 + 12 + 29 + 2 = 63%. Actual: 20 + 12 + 27 + 1 = 60%.

Condensed fictional record for this example.

Completion scenarios · not a forecast

Baseline date and two indicative rates

Contract completion20 Nov

2026 · unchanged

5 points / week25 Nov

+5 calendar days
+3 working days

4 points / week9 Dec

+19 calendar days
+13 working days

40 percentage points of physical progress remain. At 5 points per week, they take 8 weeks; at 4 points per week, they take 10 weeks. These are scenarios, not verified programme forecasts.

The first scenario extends the recent four-week rate. Both require checks of remaining sequencing, curing, striking, stair deliveries and handover.

Validate the sequence and test recovery.

Revised mezzanine details and later stair openings are constraining the current sequence. Their individual or combined effect on completion is not yet established.

Open the programme action
Open P01 · programme and scenarioBaseline dates and recent-rate calculation
Baseline dates and recent-rate calculationFictional source excerpt

Start 18 May · contract completion 20 November 2026

186 calendar days between start and finish; 187 days counting both dates. Planned Monday–Friday calendar excludes the 25 May and 31 August bank holidays.

Reported progress rose from 40% on 2 September to 60% on 30 September: 20 percentage points in 4 weeks, or 5 points per week. At that recent rate, the remaining 40 points take 8 weeks, reaching 100% on 25 November. This is a recent-rate scenario. At 4 points per week, 10 weeks remain and completion moves to 9 December.

Simple progress extrapolation, not a logic-linked programme forecast or an assessed extension of time. Check remaining sequencing, curing, strikes, stair deliveries and handover before relying on the date. The contract completion date remains 20 November; no extension is assumed.

Condensed fictional record for this example.

All amounts exclude VAT. Project margin is revenue less project costs including site overheads, before corporate overheads and tax. Margin percentage is profit divided by revenue, not markup on cost.

Changes and instructions

Separate agreed value from open discussions. Open a change to inspect the instruction and supporting records.

Agreed£180k2 changes · in forecast revenue
In discussion · TBC£210k2 changes · excluded from revenue
Disagreed£35k1 change · excluded from revenue
5 changes shown

£425,000 full submitted / estimated value. This is the whole change register, including remaining work. Completed change work at 30 September is £160,000.

V-001Core-base thickeningHEX-S-201 C03 / SI-006Agreed£90,000

What changed

Revised foundation section adds concrete and reinforcement to Core B.

Full submitted / estimated value£90,000
Completed by 30 September£90,000
Assessed / certified on 5 October£90,000
Remaining estimated work value£0

Next step · QS

Include the final agreed quantity in the valuation register.

Supporting evidence: Revised drawing comparison; Concrete delivery tickets; Signed measurement sheet.

SI-006 · Core-base thickening1 Jul 2026
1 Jul 2026Fictional source excerpt

Core-base thickening

From: Main contractor.

Record state: Confirmed.

Linked to V-001. Revised foundation section adds concrete and reinforcement to Core B.

Condensed fictional record for this example.

V-002Additional upper-level slab-edge upstandsHEX-S-341 C04 / SI-011Agreed£90,000

What changed

Additional perimeter upstands at Level 4. Formwork and reinforcement are partly complete; the remaining upstand work follows the Level 4 slab sequence.

Full submitted / estimated value£90,000
Completed by 30 September£30,000
Assessed / certified on 5 October£10,000
Remaining estimated work value£60,000

Next step · QS

Reconcile the £20,000 difference between £30,000 completed work and £10,000 assessed in PAY-05; retain £60,000 of remaining work in the forecast.

Supporting evidence: Instruction SI-011; Measured formwork and reinforcement sheet; Level 4 progress records.

SI-011 · Additional Level 4 slab-edge upstands22 Jul 2026
22 Jul 2026Fictional source excerpt

Additional Level 4 slab-edge upstands

From: Main contractor.

Record state: Confirmed.

Linked to V-002. Additional perimeter upstands at Level 4. Formwork and reinforcement are partly complete; the remaining upstand work follows the Level 4 slab sequence.

Condensed fictional record for this example.

V-003Mezzanine changed to in-situ concreteERI-018 → SI-017 / HEX-S-410 C05In discussion · TBC£145,000

What changed

A 360 m² mezzanine zone changes from the tender precast arrangement to in-situ reinforced concrete, requiring revised propping and a new pour sequence.

Full submitted / estimated value£145,000
Completed by 30 September£30,000
Assessed / certified on 5 October£0
Remaining estimated work value£115,000

Next step · Commercial manager

Submit the reconciled concrete, reinforcement and propping build-up; link the sequence impact to the programme.

Supporting evidence: Drawing revision overlay; Temporary works revision TW-07; Labour and plant allocation; Concrete and rebar invoices.

ERI-018 · Mezzanine arrangement change3 Sep 2026
3 Sep 2026Fictional source excerpt

Mezzanine arrangement change

From: Employer's Agent to main contractor.

Record state: Upstream reference; passed down by SI-017.

Linked to V-003. A 360 m² mezzanine zone changes from the tender precast arrangement to in-situ reinforced concrete, requiring revised propping and a new pour sequence.

Condensed fictional record for this example.

SI-017 · Implement the revised mezzanine details4 Sep 2026
4 Sep 2026Fictional source excerpt

Implement the revised mezzanine details

From: Main contractor to frame subcontractor.

Record state: Instructed; valuation TBC.

Linked to V-003. A 360 m² mezzanine zone changes from the tender precast arrangement to in-situ reinforced concrete, requiring revised propping and a new pour sequence.

ERI-018 is the upstream Employer’s Agent reference. SI-017 is the main contractor’s instruction to the frame subcontractor. The change is instructed; the valuation is still to be agreed.

Condensed fictional record for this example.

TW-07 · temporary works revisionLinked supporting record · V-003
Linked supporting record · V-003Fictional source excerpt

Revised propping arrangement

The changed in-situ mezzanine needs a revised temporary works and pour sequence. Keep the revision, review status and release record with the commercial change.

Condensed fictional record for this example.

V-004Additional Level 4 service openingsSI-019 / HEX-MEP-402 P06In discussion · TBC£65,000

What changed

Eight new Level 4 service penetrations require revised reinforcement and trimming details before the upcoming slab pour. Initial coordination and preparation work is complete; most of the change remains to be built.

Full submitted / estimated value£65,000
Completed by 30 September£10,000
Assessed / certified on 5 October£0
Remaining estimated work value£55,000

Next step · QS / engineer

Agree the opening schedule and measure the additional trimming bars and formwork.

Supporting evidence: Coordinated opening schedule; RFI-029 response; Rebar schedule delta; Daily production record.

SI-019 · Additional Level 4 openings11 Sep 2026
11 Sep 2026Fictional source excerpt

Additional Level 4 openings

From: Main contractor to frame subcontractor.

Record state: Instructed; valuation TBC.

Linked to V-004. Eight new Level 4 service penetrations require revised reinforcement and trimming details before the upcoming slab pour. Initial coordination and preparation work is complete; most of the change remains to be built.

Condensed fictional record for this example.

V-005Stair-landing reworkHEX-S-520 C04 / RFI-032; no confirmed instructionDisagreed£35,000

What changed

Proposed changes to a stair-landing opening would require local formwork alterations. No changed work has been carried out. The contractor considers the proposed work included in the original coordination scope; the subcontractor disagrees.

Full submitted / estimated value£35,000
Completed by 30 September£0
Assessed / certified on 5 October£0
Remaining estimated work value£35,000

Next step · Commercial manager

Reconcile the tender scope and revision history, request a written decision and keep the position separate from agreed revenue.

Supporting evidence: Tender scope matrix; Before / after drawing record; Estimate build-up / proposed method and resources; RFI-032 correspondence.

RFI-032 · Confirm stair-landing scope and formal direction15 Sep 2026
15 Sep 2026Fictional source excerpt

Confirm stair-landing scope and formal direction

From: Frame subcontractor.

Record state: Open clarification; not an instruction.

Linked to V-005. Proposed changes to a stair-landing opening would require local formwork alterations. No changed work has been carried out. The contractor considers the proposed work included in the original coordination scope; the subcontractor disagrees.

Condensed fictional record for this example.

Agreed values are £180k. In-discussion values (£210k) and disagreed value (£35k) total £245k and are excluded from forecast revenue. Completed change work is £120k agreed plus £40k unagreed; £100k has been assessed / certified. Instruction status and valuation agreement are separate.

Trace the direction through the right contract.

ERI-018 is the Employer’s Agent’s upstream reference. SI-017 passes the mezzanine change from the main contractor to the frame subcontractor. RFI-032 remains an open clarification and is not an instruction.

Inspect the mezzanine instruction

What needs to happen next

Clear owners and specific actions, linked to the records that explain why.

6 actions shown
01

Reconcile the £180k valuation gap

Base measurement £120k, V-002 agreed work £20k and completed unagreed work £40k (V-003 £30k + V-004 £10k) are not in the 5 October gross assessment.

Action: Prepare a line-by-line VAL-05 / PAY-05 reconciliation with measurements and the agreed change register.

Project QSTarget 23 Oct 2026A-01
High priority
02

Complete the mezzanine change record

V-003 is instructed but its £145k valuation is still under discussion.

Action: Link the drawing revision, instruction, daily labour and plant, production quantities, invoices and temporary works records to V-003.

Site manager / QSTarget 22 Oct 2026A-02
High priority
03

Verify required delay notices and close gaps

The revised sequence may affect completion. Existing notice history and evidence of service need verification; the dashboard does not confirm compliance.

Action: Have the commercial manager, with the appropriate contract or legal adviser, urgently check notices already issued, service records, the executed subcontract, amendments and applicable timing. Close any gaps and issue the appropriate notice if required. Do not assume compliance or an agreed extension of time.

Commercial managerTarget 22 Oct 2026A-03
High priority
04

Show the programme impact and test recovery

The recent-rate scenario reaches 25 November, 5 calendar days / 3 working days after baseline; the slower-rate sensitivity reaches 9 December, 19 calendar days / 13 working days after baseline. Neither is a verified programme forecast.

Action: Update the logic-linked programme with actual dates, mezzanine activities, stair deliveries and curing / strike durations. Test safe resequencing and record effects on follow-on trades.

Planner / project managerTarget 23 Oct 2026A-04
High priority
05

Close the stair-landing scope question

V-005 is disputed and there is no confirmed instruction.

Action: Assemble the tender scope matrix and drawing revision trail, seek written clarification and record the commercial response.

Commercial managerTarget 26 Oct 2026A-05
Medium priority
06

Confirm receipt of the certified balance

At the 21 October cash follow-up, £168,600 net certified has not yet been matched to a receipt.

Action: Check the applicable payment dates and remittance with accounts; reconcile the receipt or record the specific follow-up needed. Do not label the balance overdue without checking.

Accounts / QSTarget 23 Oct 2026A-06
Medium priority

Live-project actions were reviewed on 21 October 2026. Due dates are illustrative internal targets, not contractual notice or payment deadlines. Cost, valuation and progress are at 30 September; certification is dated 5 October and receipts are reconciled to 21 October.